Courseulles offshore wind farms
Rock installation
Rohde Nielsen was contracted to install the 82 pcs of rock beds approx. 13×18 m. at 24 locations / foundations for the Courseulles OWF.
The rock is produced at a quarry in Norway. The total amount of rocks produced was approx. 68,000 ton. All produced rocks were shipped from Norway to Saint Wandrille in France. All shipping was taken place in the period between 1st September and 2nd November 2023, in total 3 shiploads of rocks will be shipped. Shipping of rocks from Norway was ongoing during rock installation.
Before the start of loading of rocks, a pile of approx. 4 500 ton of rocks was prepared and laid along the quayside by a local stevedoring company, the pile was in reach distance of the Grane R cranes. This was continued true out the project, every time Grane R left Saint Wandrille quay a new stockpile of approx. 4500 ton was prepared.
Grane R was load herself and then transit to the offshore installation site to install the rock according to given position and design. Before installation were commenced an in-survey was be done. Installation was done by fall pipe and wire crane, during the installation surveys were done frequently, this to monitor the status of the installation, when the final design is achieved an out-survey was done. The all out-survey was immediately forward to the client, for final approval.
- Location: Courseulles (FRA)
- Scope: 62,000 ton of rocks
- Client: Saipem S.A.
- Year: 2023
The fleet that made it possible
- Grane R
Grane R
Download specifications- Hopper capacity
- 4,900t
- Length overall
- 93.00m
- Breadth
- 22.20m
- Draught loaded
- 6.50m
- Draught unloaded
- 5.40m
- Dredging/Installation depth
- up to 100.00m
Other projects
Cockburn Sand Supply
Explore Project
Purpose:
Supplying of shell sand, dredged from a specific area, offshore at Owen Anchorage, West Australia….
- Location:
- Owen Anchorage, Western Australia
- Scope:
- 1,500,000 m³ annually
- Client:
- Cockburn Cement Ltd.
- Year:
- 2018-2030
Bunbury
Explore Project
Purpose:
Maintenance dredging within the Port of Bunbury….
- Location:
- Bunbury, Australia
- Scope:
- 200,000 m³ annually
- Client:
- Southern Ports Authority
- Year:
- 2018-2023
Storstrøm Bridge
Explore Project
Purpose:
Dredging of temporary work channels and other various tasks…
- Location:
- Zealand, Denmark
- Scope:
- 923,000 m3
- Client:
- Storstroem Bridge Joint Venture I/S
- Year:
- 2019-2023
Seabed Boulder Removal
Explore Project
Purpose:
Preparation for the arrival of a jackup vessel to repair a wind turbine generator…
- Location:
- Wikinger OWF (GER)
- Scope:
- 22 pcs
- Client:
- Siemens Gamesa
- Year:
- 2023
Courseulles offshore wind farms
Explore Project
Purpose:
Installation of 82 pcs of rock beds approx. 13×18 m. at 24 locations…
- Location:
- Courseulles (FRA)
- Scope:
- 62,000 ton of rocks
- Client:
- Saipem S.A.
- Year:
- 2023
Guyana
Explore Project
Purpose:
A long time charter contract for continuous maintenance dredging in entrance channel…
- Location:
- Berbice river, Republic of Guyana
- Scope:
- 160,000,000 m3
- Client:
- Bauxite Company of Guyana Inc. (BCGI)
- Year:
- 2011- 2020
Sao Luis
Explore Project
Purpose:
Maintenance dredging at Pier 1; Pier 3 North and South; Pier 4 North and South…
- Location:
- São Luís, Brazil
- Scope:
- 5,037,152 m3
- Client:
- Vale SA
- Year:
- 2015-2020
Klaipeda
Explore Project
Purpose:
About 30,000 m3 of moraine soil needs to be removed and dumped in offshore dumping grounds….
- Location:
- Klaipeda, Lithuania
- Scope:
- 70,000 m3
- Client:
- Klaipeda State Seaport Authority/BMGS
- Year:
- 2020
Paldiski
Explore Project
Purpose:
Capital Dredging and securing slope of the Quay number 7….
- Location:
- Paldiski, Estonia
- Scope:
- 600,000 m3
- Client:
- Ports of Tallinn
- Year:
- 2019-2020
Cairns
Explore Project
Purpose:
Deepening and widening of the harbor and entrance channel located at the Great Barrier Reef Marine Park…
- Location:
- Cairns, Australia
- Scope:
- 750,000 m3
- Client:
- Ports North
- Year:
- 2019
Vordingborg Port
Explore Project
Purpose:
Deepening of the shipping channel to 10.4 meters and a width of 70 meters…
- Location:
- Vordingborg, Denmark
- Scope:
- 1,800,000 m3 sand, 1,610,000 of boulder clay
- Client:
- Munck Havne og Anlæg A/S
- Year:
- 2018-2019
Talk to us about your next project
Would you like to know more about us and our services? Rohde Nielsen operates globally as a general contractor as well as a subcontractor.
Get in touch